| January 16, 2006 |

The old partition walls are removed and new studs go up for the bookmobile
office expansion in the basement
|

Despite the mud caused by warm temperatures and rain and snow, cement
blocks and bricks are put in place for the new elevator
|
| January 23, 2006 |

The microfilm and magazine area of the reference department and the office
area are stripped of asbestos in preparation for renovation
|

A large fork lift crane is used to lift roofing materials for the new
program room
|
| January 30, 2006 |

Materials to be used on the roof of the programming room addition are
lifted by a tall crane
|

The "circle wall" by the center stairway has been removed for
refurbishing off-site
|
| February 6, 2006 |

The hallway to the library offices is prepared for new ceilings, wiring,
and walls
|

Here's a glimpse behind the temporary construction walls in the reference
department. This area will house reference offices and the computer
classroom
|
| February 13, 2006 |

The former Alliance Room space is prepared for its new use as a computer
classroom
|

The computer classroom will have half windows overlooking the reference
desk area
|
| February 20, 2006 |

Walls go up for the Extension Services offices in the basement
|

The reference
desk area has plenty of room for public computers
|
| February 27, 2006 |

Walls in the Extension Services offices are prepared for painting
|

Technical processing space is tight as the walls for the systems
department are added
|